Number | Mathematical Skills | Applications |
---|---|---|
1 | Number, percentages, and percentiles | Determining the amounts, costs, and dimensions of materials |
2 | Ratio | Scaling models, dimensions, shapes, and drawings |
3 | Surface area/Volume | Finding costs of quantities, waste amounts |
4 | Trigonometry | Calculating angles/lengths of products |
5 | Graphs and charts | Using data to make decisions/visualization of data |
6 | Coordinates and geometry | Using coordinates for design drawings |
7 | Statistics | Using data to make informed design decisions |
A cement manufacturer is to provide concrete for a new high speed railway within the UK.
Calculate whether the cement manufacturer can meet the construction companies cement demand.
Step 1) Calculate the construction companies demand in kg per day:
Demand = 500 x 450 = 225,000kgStep 2) Convert demand in kg to tonnes:
Demand in tonnes = 225,000⁄1,000 = 225 tonnesStep 3):
As demand is greater than supply the manufacturer cannot meed the demand of the construction company
A new high speed railway will decrease the time taken to travel between London and York by 15 minutes. The journey takes 2.05 hours currently. Calculate the percentage reduction in travel time.
Step 1) Calculate the current journey time in minutes:
Time (minutes) = 2.05 x 60 = 123 minutesStep 2) Calculate the new journey time:
New time = 123 - 15 = 108 minutesStep 3) Calculate the percentage reduction in journey time:
Percentage reduction = Old - New⁄Old = 15⁄123 = 0.122 = 12.2%
The budget os this high speed railway was estimated to cost £50 million, however, due to rising costs the company responsible estimate the cost will increase by 57%. Work out the new cost of the railway project.
Step 1) Convert the percentage increase into a decimal:
57% = 0.57Step 2) Calculate the new cost of the project:
New time = 50 x (1 + 0.57) = £78.5 million